The West Lake Drive Bridge Replacement Project

The City of Fort Lauderdale, working with Jacobs Engineering Group as its design consultant, is planning to replace the three bridges that carry West Lake Drive over the Estelle, Lucille and Mercedes Rivers.

The three bridges

Estelle River

Estelle River Bridge

West Lake Drive — northern crossing, north of Lucille Drive

Bridge No.
865771
City Project
P12860
FDOT Project
450868-1-52-01

Lucille River

Lucille River Bridge

West Lake Drive — middle crossing, between Lucille Drive and Mercedes Drive

Bridge No.
865773
City Project
P12861
FDOT Project
450866-1-52-01

Mercedes River

Mercedes River Bridge

West Lake Drive — southern crossing, south of Mercedes Drive

Bridge No.
865774
City Project
P12858
FDOT Project
450867-1-52-01
The three West Lake Drive crossings in Harbor Beach, Fort Lauderdale. Marker positions from OpenStreetMap.
Existing West Lake Drive bridge rail stenciled with bridge number 865774
The Mercedes River bridge (No. 865774) today.
Existing low West Lake Drive bridge over a Harbor Beach waterway
The low, open profile of West Lake Drive’s existing crossings.

What the City proposes

The City’s official project description states that the current project includes replacing the three bridges with one travel lane in each direction, reconstructing roadway approaches, upgrading signage and pavement markings, and milling and resurfacing.

The City’s current estimate is a construction cost of approximately $13.8 million, with the design approximately 60% complete as reported in 2026, and construction scheduled from fall 2027 through summer 2030.

Why the City says replacement is needed

The City’s FY2026 capital documents, drawing on FDOT-based inspection classifications, describe:

  • Lucille River Bridge: “structurally deficient,” with inspection frequency increased to every three months.
  • Mercedes River Bridge: “structurally deficient,” with inspection frequency increased to every six months.
  • Estelle River Bridge: “functionally obsolete,” with inspection frequency increased to every three months.

These classifications are the City’s and FDOT’s stated project justification — not an independent Harbor Beach Association engineering conclusion.

Residents are not asking to substitute their judgment for engineers’. They are asking for an independent evaluation of whether rehabilitation or reinforcement could safely extend the useful lives of the structures before complete replacement becomes irreversible.

Project history

  1. June 2023

    Design work announced

    The City announced design work for the three Harbor Beach bridges.

  2. October 2023

    Field work completed

    The City reported that surveying, geotechnical analysis and waterway inspection work was completed.

  3. April 11, 2024

    First public meeting

    The City held its public meeting for the West Lake Drive bridges. At that time, the City listed the estimated construction cost at approximately $9.2 million, with construction beginning in fall 2028.

  4. March 12, 2026

    Second public meeting

    The City held a new public meeting and reported the design as approximately 60% ready, the construction estimate as $13.8 million, and anticipated construction from fall 2027 to summer 2030.

  5. April – Fall 2026

    Separate repair project underway

    In a separate project, the City's contractor, Engineer Control Systems, began temporary-support and structural-concrete repairs to the West Lake Drive bridge between E. Lake Drive and Mercedes Drive, with work expected through fall 2026.

The City’s published figures moved from an estimated $9.2 million and a fall-2028 construction start (2024) to $13.8 million and a fall-2027 start (2026). Both figures are the City’s own; the earlier one is historical context, not the current budget. Source documents are collected on the Documents page.